| Turkerler Insaat |
Istanbul Zincirlikuyu Ciftciler / Ciftci Tower |
Shoring and excavation |
15/10/2012 - 01/04/2013 |
-
| Eksen Insaat |
Adapazarı Kaynarca Karasu Road |
Φ 100 cm bored pile for bridges |
30/09/2012 - 01/04/2013 |
-
| Durmazlar Plaza Bursa |
Bursa Durmazlar Plaza |
Φ 120 cm bored pile for Bursa Durmazlar Plaza Foundation |
25/11/2012 - 01/04/2013 |
-
| KOLIN INSAAT |
İzmir Ringroad Cigili Aliaga Km:00+000-29+000 Motorway |
Diameter 120 cm, L=42 cm bored pile |
01/07/2012 - 12/2012 |
-
| Hyundai Assan-Kocaeli |
Hyundai Assan-Kocaeli |
Soil improvement with Φ 60 diameter jet grout. |
2012 - 12/2012 |
-
-
-
| GAMA-NUROL ADI ORTAKLIGI |
Marmaray Project Uskudar ve Yenikapi Istasyonu Soil Injection |
750.000 m Cooling tube injection |
08.12.2009 - 31.12.2009 |
-
| OZD INSAAT |
Ali Fuat Pasa Anchorage Retaining Wall |
Anchorage Retaining Wall |
01/2011 - 05/2012 |
-
| TOKI |
Karasu State Hospital Soil Improvement |
16000 m, 60 cm jet grout |
01/2011 - 04/2011 |
-
-
| INANLAR INSAAT |
Istanbul, Sisli, Ferikoy |
Excavation Bracing System Practice: 65 cm Bored Pile, 30 cm Mini Pile, Foundation On Wells, Anchorage |
01/2010 - 15//03/2011 |
-
| HASOGLU YAPI |
Hasoglu Yapı Pile Loading Test |
Designing Ø100 cm 40 m tall pile loading test’ piles that reach 2000 ton loading capacity, test and reaction piles, joist manufacturing and test preperations for residence project - Hasoglu Yapı Beylikduzu 44 floor hotel. |
10/2010 - 10/2010 |
-
| HASOGLU YAPI |
Hasoglu Yapı Pile Loading Test |
Designing Ø100 cm 40 m tall pile loading test’ piles that reach 2000 ton loading capacity, test and reaction piles, joist manufacturing and test preperations for residence project - Hasoglu Yapı Beylikduzu 44 floor hotel. |
10/2010 - 10/2010 |
-
| ATASEHIR KONUT |
Atasehir Housing Project Bracing Manufacturing |
Bracing manufacturing was made with soil nailed shotcrete for Atasehir hpusing project's excavation. |
24/08/2011 - 02/09/2011 |
-
| IL OZEL IDARESI |
Sultanbeyli School Construction Site Bracing Manufacturing |
Soil nailed bracing manufacturing was made for building excavation reinforce system in Sultanbeyli school construction site. |
08/2011 - 09/2011 |
-
| HUSEYIN KALKAVAN |
Golcuk School Project Soil Improvement |
The soil improvement with Ø 60 cm 15 cm tall jet grout for Huseyin Kalkavan Construction Golcuk school project. |
08/2011 - 09/2011 |
-
| OZDEMIR INSAAT |
Geyve Connection Road Jet Grout Manufacturing |
Jet grout was manufactured for repairing the liquefaction of more than 5m-8m approach fill and risk of fill external stability to Geyve connection road‘s viaduct approach. |
05/2011 - 09/2011 |
-
| HASOGLU YAPI |
Hasoglu Yapi Pressiometer Tests |
Pressiometer tests were made 1,5m intermittently in 50 m depth drillings for Hasoglu Yapı 44 floors Residents foundation design project |
08/2011 - 09/2011 |
-
| YMN GROUP |
Emaar Properties Hadimkoy Toskana Villa Project |
Emaar Hadimkoy villa project reinforced excavation wall's fill was made in-situ test and control |
08/2011 - 09/2011 |
-
| IYTE |
Izmir Institute Of Technology & Tubitak Project |
CPT, CPT U and SCPT were made in 26 points for Izmir Institute Of Technology & Tubitak Project |
07/2011 - 09/2011 |
-
-
| CENGIZ & ICTAS & BELEN |
Eskisehir Istanbul C.I.B. High-speed Train Project |
Landslide Exploration Drilling |
09/2011 - 09/2011 |
-
| ACILIM INSAAT |
Golcuk Altinova Manufacture Of Slope Support Structure With The Soil Nail |
Manufacture of Slope Support Structure with Soil Nail, Barbacane, Shotcrete. |
10/2010 - 28/02/2011 |
-
| CORLU ARMADA EVLERI |
Corlu Mimart Soil Amendment by Jet Grout |
The soil amendment under block by 60/80 cm jet grout |
10/2010 - 03/2011 |
-
| GOLCUK BELEDIYESI |
Slope Stabization by Soil Nail |
Slope stabization by soil nail |
11.11.2010 - 05.01.2011 |
-
| GEOTEKNIK A.S. |
Istanbul – Eskisehir High Speed Train Project Jetgrout-2 |
Ø80 Jetgrouting 40.000 m |
14.07.2010 - 25.12.2010 |
-
| CIZGI MUH |
Turkmenistan / Awaza Area hotel construction under Foundation Jetgrout Production |
Ø80 Jetgrouting 10.000 m |
30.01.2010 - 15.02.2010 |
-
| STFA INS |
Turkmenistan / CPT Tests done in the Caspian region |
45 CPT |
10.10.2010 - 01.01.2011 |
-
| STY INSAAT |
Malatya – Darende Road Karahan Passage, Karahan Tunnel Project, Jetgrouting |
Ø80 Jetgrout-2 İmalatı 30.000 m |
08.10.2010 - 12.12.2010 |
-
| ISKAY INSAAT |
Unye Motorway Passage Bridge Piers, Bored Pile |
Ø120 Bored Pile 15.000 m |
25.09.2010 - 15.12.2010 |
-
| EGF INSAAT |
EGF Insaat Kozyatagı Shoring Project Of Bussiness Center |
Soil Nail, Shotcrete, -11,00 foudation excavation with shoring |
10.03.2010 - 15.05.2010 |
-
| GOKBORA A.Ş. |
GOKBORA – Sekerpinar Warehouse Area Section-2. Foundation Base Jetgrout Project |
Ø80Jetgrouting 6.500 m |
11.04.2010 - 20.05.2010 |
-
| GEOTEKNIK A.S. |
Ayber Insaat Yesilköy – Opet Soil Improvement Project |
Ø80Jetgrouting 23.750 m |
28.04.2010 - 05.06.2010 |
-
| TURAN INS. |
Catalca-Kabakca railway line from +300 70 - 70 +450 km Ground Improvement Project |
Ø80 Jetgrouting 7000 m |
24.06.2009 - 04.08.2009 |
-
| OZDEMIR INS. A. S. |
Adapazari-Mekece State road in Ali Fuad Role 2nd Phase Application of Permanent Anchorage project |
Permenant Anchorages 18.000 m |
01.06.2009 - 10.10.2009 |
-
| SEN MERMER |
Bahcekoy Istanbul University Faculty of Forestry Football Area Tribune Construction Retaining Works |
Ø45 Mini Piles 2305 m, Permenant Anchorages 1500 m |
10.05.2009 - 15.06.2009 |
-
| SEYIT UCAR |
Gurpinar Residential Construction Retaining Project |
Ø30 Mini Piles 1200 m, Anchorages 780 m |
25.05.2009 - 29.06.2009 |
-
-
-
| ISTAC A.S. |
Odayeri Solid Waste Sanitary Landfill Waste Water Pool Soil Improvement Practices |
Ø80 Bored Piles 2281m , Injection 6225 m, 1x1 m Pile Cap 199 m |
05.03.2009 - 03.05.2009 |
-
| GAMA-NUROL ADI ORTAKLIGI |
Marmaray Project Uskudar Station work done in foundation injection |
240 noktada Injection |
11.02.2009 - 21.03.2009 |
-
| BITIRIM TIC. |
Bitirim Trade Gurpinar Residential Construction Retaining Piles |
Ø45 Mini Piles 708 m |
11.02.2009 - 07.03.2009 |
-
| BULUTLAR INS. |
Esenyurt Seyhan YIGIT's Building Construction Retaining Works |
Ø45 Mini Piles 1900 m |
02.02.2009 - 28.03.2009 |
-
| TAS ZEMIN INS |
AMASYA Midilli Regulator and HES Project |
Ø100 Jetgrouting 9460 m |
30.12.2008 - 01.03.2009 |
-
| BAYINDIRLIK ve ISKAN MUDURLUGU |
Istanbul Tuzla Sb.Astsb. Housing Construction Land |
Subsoil Investigation Boreholes, Laboratory ve In-situ Tests |
28.12.2008 - 05.01.2009 |
-
| TES-IS INS |
Gebze RESINEX Pelitli Plastic Factory Storage Construction Soil Improvement Application |
Injection micropile 2499.75 m |
18.10.2008 - 20.11.2008 |
-
| Ismail CAM |
Istanbul Kırac Residential Construction Retaining Works |
Ø45 Mini Piles 484 m, Anchorages 144 m |
18.09.2008 - 10.10.2008 |
-
| ILPA INŞ. |
Silivri Cantakoy Factory Construction Under Foundation Piles |
Ø65 Bored Piles 1900 m |
18.08.2008 - 15.09.2008 |
-
| LIMAK INS. |
Bozuyuk-Mekece Road Improvement Project |
Ø60-Ø80-Ø100 Jetgrouting 11.642 m |
25.06.2008 - 25.08.2008 |
-
| SANAT YAPI |
Yol Bulan Metal K.Bakkalkoy Business Center construction |
Ø30 Mini Piles 2316 m, Anchorages2884 m, 0.4x0.4 m Pile Cap 101 m, 0.3x0.7 m Crossbeam 299 m |
15.08.2008 - 12.11.2008 |
-
| LIMAK INS. |
Duzce-Akcakoca-Eregli Road improvement project |
Soil Improvement Project |
01.05.2008 - 25.05.2008 |
-
| TOPLU KONUT IDARESI BASKANLIGI |
Bolu Mengen Pazarköy Mah.Derekapı Role, Role of Afyon İscehisar Sırçalık, Geological, Geophysical and Geotechnical Investigation Works |
Subsoil Investigation Boreholes, Laboratory and In-situ Tests |
16.05.2008 - 15.06.2008 |
-
| TES-IS INS |
Gebze Pelitli Resinex Factory Location Area Filling soil Improvement Works |
Ø60 - Ø80 Jetgrouting 4000 m |
13.05.2008 - 20.06.2008 |
-
| GOKBORA |
Gokbora Akiırat Storage Construction under foundation Jetgrout column |
Ø80 Jetgrouting 6000 m |
05.05.2008 - 20.06.2008 |
-
| Mustafa KILINCOGLU |
Yeşilova Mah.Akdeniz Cad. No:7 parcel Building Construction Retaining Works |
Ø30 Mini Piles 888 m, Anchorages 494 m |
01.05.2008 - 25.05.2008 |
-
| AYSON A.S. |
Harbiye Convention Center Construction Retaining Works |
Ø30 Mini Piles (Pneumatic)682 m |
15.04.2008 - 01.05.2008 |
-
| BANDIRMA BELEDIYESI |
Slopes Stabilized Analysis Beside The Chamber Of Mechanical Engineering Bandirma Representation |
Subsoil Investigation Boreholes, Laboratory and In-situ Tests |
14.03.2008 - 30.04.2008 |
-
| Omer SOLA |
Istanbul G.O.P Kuçukkoy Mevlana Mah.879/1 Sok.N.5 Indoor Mini Pile |
Ø25 Mini Piles 300 m within Existing Structure Basement Floor |
14.02.2008 - 01.03.2008 |
-
| OZBAKIR INS. |
Soil Improvement Project for Eskişehir Mutalip Meslek High School Construction |
Ø80 Jetgrouting 5039.50 m |
19.03.2008 - 04.05.2008 |
-
| CAN TEKSTIL |
Tekirdag-Corlu Can Textile Factory 1 and 2 Greenhouse Area soil improvement Project |
Ø60-Ø80 Jetgrouting 40002.50 m, Ø30-Ø45 Mini Piles 14000 m |
20.07.2006 - 12.08.2008 |
-
| BURAK TOK |
Kuleli Military High School Social Facility Worksite Mini Piles |
Ø25 Mini Piles 750 m |
11.01.2008 - 30.01.2008 |
-
| Adnan SEN |
Bursa Nilüfer County Beşevler |
Anchorages |
24.12.2007 - 10.01.2008 |
-
| Daniel OZYUREK |
Istanbul Hadimkoy Karaagac Village Daniel OZYUREK's area Bored Pile Produced |
Ø80 Bored Piles 180 m, 1x1 m Pile Cap 30 m |
07.12.2007 - 17.12.2007 |
-
| RENKTAS INS. |
Sariyer Yusuf Ziya Onis Stadium extra tribune project soil improvement application |
Ø60 Jetgrout 5002.50 m |
15.10.2007 - 22.11.2007 |
-
| TEKCELIK INS |
Construction of Parking under Gunesli THY blocks Retaining Works |
Ø30 Mini Piles 960 m, Anchorages 420 m |
10.09.2007 - 15.11.2007 |
-
| ARTIKA YAPI |
Yalova Esenkoy Residential Construction Worksite Retaining Works |
Ø25 Mini Piles 350 m, Anchorages585 m |
09.10.2007 - 07.11.2007 |
-
| YUK.MIMAR AHMET EKTEM |
Eminonu District, Sultanahmet Role under foundation mini piles |
Ø30 Mini Piles 800 m |
03.10.2007 - 15.10.2007 |
-
| BOS YAPI INS. |
Hadimkoy Road 174, 2 Parcel Total Gas Station Under Foundation Piles |
Ø45 Mini Piles 208 m |
01.08.2007 - 20.08.2007 |
-
| TIMSA TAAH. INS. LTD. STI. |
Esenyurt Goktaslar Et Construction Retaining Works |
Ø80 Bored Piles 910 m, Ø65 Bored Piles 630 m, 1x1 m Pile Cap 40 m, 0.85x0.6 m Pile Cap 58 m, 0.3x0.5 m Pile Cap 344m, Anchorages 6439 m |
01.05.2008 - 01.09.2008 |
-
| SAKA INS. |
Beyoglu German High School Modernization and Soil Reinforcement Project |
Ø25 Mini Piles (within Existing Structure Basement Floor ) 1077.40 m |
15.11.2007 - 18.12.2007 |
-
| Sedat OZALTIN |
ISKI Headquarters treatment pools cavities filled with injection |
4 Treatment Reservoir Injection |
18.09.2007 - 30.09.2007 |
-
| BUYUKCEKMECE BELEDIYESI |
Buyukcekmece Municipality Amphitheatre Side Retaining Piles |
Ø45 Mini Piles 800 m |
05.08.2007 - 13.08.2007 |
-
| ACT INS. |
Anatolian Side microzonation Report , Maps and Cone Penetration Test (CPT) |
Microzoning Project Cpt |
20.07.2007 - 20.06.2008 |
-
| Adil CELIK |
Bagcılar Evren Mah.Çam Sok.No:8 parcel Building Construction Retaining Works |
Ø45 Mini Piles 700 m |
10.07.2007 - 23.07.2007 |
-
-
| INTEM INS |
Intem Ins. Kirac Town Factory Construction |
Ø65 Bored Piles 672 m, Anchorages |
24.06.2007 - 31.07.2007 |
-
| TEKNOFOR INs. |
Garanti Koza-Alsim Alarko Seyrantepe Metro Construction Storage Area Retaining work |
Temporary and Permenant Anchorages 16521 m, Soil Nail1206 m. |
10.04.2006 - 09.06.2007 |
-
| Erol CEPNI |
Haramidere Baycan Factory construction area Mini Piles |
Ø45 Mini Piles 200 m |
12.10.2006 - 20.10.2006 |
-
| SABRI DOGAN |
Istanbul Cad. Beyaz Zambak Sok. Bakirkoy Business Place Construction Retaining Works |
Ø30 Mini Piles 652.80 m, Anchorages 578 m, 0.4x0.4 m Pile Cap 43 m, 0.3x0.7 m Waler beam 42 m |
15.02.2007 - 22.03.2007 |
-
| ISTANBUL BUYUKSEHIR BELEDIYESI |
CPT test (800-point) for preparation of the microzonation Report and Mapping (South Section) |
CPT |
18.12.2006 - 12.04.2007 |
-
| CAN TEKSTıL |
Can Textile Integrated Plant Geotechnical and Geological investigation |
Subsoil Investigation Boreholes |
10.12.2006 - 15.12.2006 |
-
| YAPI TASARIM |
Maslak Forest Enterprise existing building side retaining piles |
Ø45 Mini Piles 650 m |
15.11.2006 - 25.11.2006 |
-
| ISTAC A.S. |
Kucukcekmece Hamamderesi Creek Rehabilitation Project Geological Geotechnical Engineering Consulting Services |
Consulting Services |
15.10.2006 - 20.12.2006 |
-
| ULAsIM PLANLAMA |
Kartal Sanayi cad.-Yakacık cad. intersection soil investigations |
Subsoil Investigation Boreholes |
12.10.2006 - 15.10.2006 |
-
| KULTUR KOLEJI |
Gurpinar Course Mini Pile |
Ø30 Mini Piles |
10.10.2006 - 20.10.2006 |
-
| SARAY ALUMINYUM |
Alkoop Saray Aluminum Factory Soil Reinforcement Project |
Ø60 Jetgroting 5000 m |
15.09.2006 - 30.10.2006 |
-
| SARAY ALUMINYUM |
Alkoop Saray Aluminum Factory Soil Investigation Report |
Subsoil Investigation Boreholes |
05.09.2006 - 08.09.2006 |
-
| GUNERI INS. |
Kavacik Beykoz Cumhuriyet Cad. 797 Business Center with parking lot construction Retaining Works |
1400 m2 Shoring |
13.09.2006 - 15.11.2006 |
-
| CAGLAR YAPI |
Caglar Yapı Residential Construction Retaining Works |
Ø30 Mini Piles 1000 m, Anchorages 900 m,0.5x0.5 m Pile cap 55 m, 0.3x0.7 m Waler Beam 42 m |
16.09.2006 - 12.10.2006 |
-
| GUN INS. |
Avcilar Hospital Annex Building Construction Retaining Works |
Ø30 Mini Piles 3700 m, Anchorages 3600 m |
03.08.2006 - 15.11.2006 |
-
| YASAR YILMAZ |
Tekirdag-Corlu Yasar YILMAZ Business Center Retaining Works |
Ø45 Mini Piles 984 m, Anchorages 544 m |
01.09.2006 - 27.10.2006 |
-
| ADNAN MERIC |
Avcilar business centers Soil Improvement doing indoor Injection |
Injection |
12.09.2006 - 24.09.2006 |
-
| IRFAN CENGIZ |
Soil Improvement Study for Beykoz Mansions Irfan Cengiz's Villa |
Injection |
02.09.2006 - 11.09.2006 |
-
| KILCI INS. |
Soil Research Drilling And Opening Research Hole Halkali |
Subsoil Investigation Boreholes |
25.08.2006 - 28.08.2008 |
-
| KILCI INS. |
Seismic measuring of 549 zone Halkalı |
Seismic Measurements |
23.08.2006 - 25.08.2008 |
-
| KILCI INS. |
Making of 40 CPT Test Haci Mehmet Village of Yalova |
CPT |
19.08.2006 - 22.08.2006 |
-
| KILCI INS. |
Production of Soil Research Drilling in Haci Mehmet Village Yalova |
Subsoil Investigation Boreholes |
17.08.2006 - 19.08.2006 |
-
| T.C. BAYINDIRLIK VE ISKAN BAKANLIGI |
Geotechnical Project of Sariyer Rotary 100.Yıl Anatolian High School Surrounding and Retaining Structures |
Subsoil Investigation Boreholes |
13.08.2006 - 17.08.2006 |
-
| KILCI INS. |
19 blocks soil Investigations under the TOKI works on behalf of Kuzu Insaat |
Subsoil Investigation Boreholes 380 m |
31.07.2006 - 13.08.2006 |
-
-
| ALI AYKUT |
Istanbul Sefakoy Aykutlar Tekstil Annex Building Construction Retaining Wall |
Ø30 Mini Piles 643.60 m, Anchorages 325 m , 0.4x0.4 m Pile Cap 57.65 m, 0.3x0.7 m Waler Beam 45.55 m |
20.07.2006 - 30.08.2006 |
-
| M. Ali YALCINKAYA |
Kuçukcamlica Worksite |
Ø30 Mini Piles 1000 m, Anchorages 900 m, 0.4x0.4 m Pile Cap 50 m, 0.3x0.7 m Waler Beam 150 m |
21.06.2006 - 15.07.2006 |
-
| ACARLAR |
Acarkent T2-T14-T33 No. Blocks Piled Foundation |
Ø65 Bored Piles 1500 m |
02.06.2006 - 30.06.2006 |
-
| TRAKYA JEOETUD |
Center of Edirne, Soil Research Drillings |
Subsoil Investigations |
01.06.2006 - 06.06.2006 |
-
| FERHAT OTO. SAN. TIC. LTD. STI |
Avcilar Gumuspala Feeder road Location Site Retaining Wall Construction |
Ø30 Mini Piles 550 m, Anchorages 400 m |
27.05.2006 - 20.06.2006 |
-
| ANADOLU YER BILIMLERI |
Soil improvement half basement Mansion in Catalca |
Injection |
12.05.2006 - 19.05.2006 |
-
| ISTAC A.S. |
Kucukcekmece Hamamderesi Creek Rehabilitation and Waste Water Collector Geotechnical Project |
Geotechincal Design Project |
06.05.2006 - 10.05.2006 |
-
| DOST INS.- ACARLAR INS. |
Beykoz Cavusbası Village Map 1-2, Parcel 6 Soil Investigation |
Subsoil Investigation Boreholes |
01.05.2006 - 05.05.2006 |
-
| ISKI |
Yesilkoy New TASIS Course Soil investigation |
Subsoil Investigation Boreholes |
10.04.2006 - 13.04.2006 |
-
| ULASIM PLANLAMA |
Kavacik Riva Highway-Yanık Bridge Connection Soil Investigation |
Subsoil Investigation Boreholes |
06.04.2006 - 09.04.2006 |
-
| ULASIM PLANLAMA |
Bahcesehir Input Output Highway Connection TEM Highway Connection Soil investigation |
Subsoil Investigation Boreholes |
03.04.2006 - 05.04.2006 |
-
-
| T.C.BAYINDIRLIK VE İSKAN BAKANLIĞI |
Fatih Veledi Karabas Mah. Muhittin Akdik I.O.O. Subsoil Investigation Boreholes |
Subsoil Investigation Boreholes |
28.03.2006 - 29.03.2006 |
-
| YILDIZLAR INS. |
Gungoren Tic. Mes. Lisesi Soil Improvement Project and the Application For Landslide Region |
Ø100 Bored Piles 3294 m |
17.03.2006 - 17.04.2006 |
-
| ULASIM PLANLAMA |
TEM Highway Seyrantepe Sector Soil Investigation |
Subsoil Investigation Boreholes |
25.03.2006 - 27.03.2006 |
-
| ULASIM PLANLAMA |
Eyup Topcular Cad. - Otakcılar Cad. Eyup Boulevard Intersection Soil Investigation |
Subsoil Investigation Boreholes |
22.03.2006 - 24.03.2006 |
-
| GOKKORLAR MUH. |
Bahcelievler Social Services and Child Protection Agency Seyh Zayed Child Care Sevgi Evleri Residential Area Soil Investigation |
Subsoil Investigation Boreholes |
18.03.2006 - 21.03.2006 |
-
| ULASIM PLANLAMA |
Etiler Cengiz Topel Cad. Tem Link Road Soil Investigation |
Subsoil Investigation Boreholes |
15.03.2006 - 17.03.2006 |
-
| ULASIM PLANLAMA |
Mevlana cad. - Hoca Ahmet Yesevi Cad. Intersection Soil Investigation |
Subsoil Investigation Boreholes |
10.03.2006 - 14.03.2006 |
-
| ULASIM PLANLAMA |
Bagdat Cad. ve Icadiye cad. Intersection Soil Investigation |
Subsoil Investigation Boreholes |
02.03.2006 - 10.03.2006 |
-
| ECZACIBASI |
Gebze O.S.B.Sekerpınar Koyu Eczacıbası Storage Field Geological-Geotechnical Investigation |
Subsoil Investigation Boreholes |
10.02.2006 - 17.02.2006 |
-
| SUAK INS. |
Bored Pile and injection for Eyup Historical Bath |
Bored Piles ve Injection |
31.01.2006 - 25.01.2006 |
-
| ARITES LTD. STI. |
Alkent Guvercin Sok. No. 82 Pool Construction Under Foundation Piles |
Ø30 Mini Piles 216 m |
30.01.2006 - 07.02.2006 |
-
-
-
-
| Ali YALCIN |
Istanbul Kırac Ali Yalcın Housing Construction Retaining Piles |
Ø30 Mini Piles 240 m |
15.01.2006 - 25.01.2006 |
-
| CAGDAS INS. |
Located in the T.O.S.B 63 no parcel Factory Construction under foundation piles |
Ø30 Mini Piles 800 m |
21.01.2006 - 31.01.2006 |
-
| SEN MERMER |
Construction of Silivri Stadium Tribune Retaining Piles |
Ø45 Mini Piles 130 m |
14.01.2006 - 17.01.2006 |
-
| ULASIM PLANLAMA |
Eyup Junction-Ayvansaray- Savaklar ,Eyup Junction Soil Investigation |
Subsoil Investigation Boreholes |
19.01.2006 - 24.01.2006 |
-
| MAK-YOL INS. |
Marmara Ereglisi Junction Bridge Seyman Road Bridge Soil Investigation |
Subsoil Investigation Boreholes |
15.01.2006 - 18.01.2006 |
-
| MAK-YOL INS. |
Corlu Civilian Airport Bridge Junction Soil Investigation |
Subsoil Investigation Boreholes |
10.01.2006 - 15.01.2006 |
-
| NUH CIMENTO SAN. A.S. |
Nuh Cimento Ambarli Field Soil Research Drillings |
Subsoil Investigation Boreholes |
01.01.2006 - 12.01.2006 |
-
| ULASIM PLANLAMA |
Kucukcekmece Hamamderesi Kumcular-Kasapcesme Role Creek Rehabilitation Project |
River Rehabilitation Design Project |
05.01.2006 - 11.01.2006 |
-
| T.C KARAYOLLARI |
Adapazari-Ferizli Karasu Role soil improvement application |
Ø45 Stone Column |
05.12.2005 - 15.01.2006 |
-
| T.C KARAYOLLARI |
Adapazari-Ferizli Karasu Geotechnical Project against under Fill Problem |
Geotechincal Design Project |
02.11.2005 - 09.11.2005 |
-
| ISTANBUL MAKINE VE IMALAT SANAYICILERI |
Kocaeli-Gebze Geological-Geotechnical Investigation for Infrastructure Purposes |
Subsoil Investigation Boreholes, Trial Pits, Pressuremeter, Seismic Measurements, Rezistivity |
01.11.2005 - 24.11.2005 |
-
| EKO INS. |
Adapazari-Karasu- Akcakoca Road between 30+000 - 40+000 Road Constructionand Soil Improvement |
Ø45 Stone Column 1500 m |
17.10.2005 - 31.10.2005 |
-
| MERIT INS. |
Merit Insaat Haseki Worksite Under Foundation Piles |
Ø30 Mini Piles 270 m |
25.10.2005 - 03.11.2005 |
-
| EDIRNE IL OZEL IDARESI |
Edirne - Historic Tunca - Meric Bridge |
20 Subsoil Investigation Boreholes and Core Retrievel |
16.09.2005 - 22.11.2005 |
-
| TES-IS INS. |
Gebze/KOCAELI Tes-is Insaat under foundation piles |
Ø30 Mini Piles |
02.10.2005 - 20.10.2005 |
-
| ULASIM PLANLAMA |
Umraniye Aksekili M.Uslu Junction Soil Investigations for the Construction of Overpass |
Subsoil Investigation Boreholes |
30.09.2005 - 02.10.2005 |
-
| KARABUK BELEDIYESI |
KarabUk-Fatih Geotechnical Investigation for Land Use Suitability |
Subsoil Investigation Boreholes |
28.09.2005 - 10.10.2005 |
-
-
-
| AYVEL INS. |
Tekirdag-Corlu Tube Mercerized Factory Soil Improvement Application |
Ø45 Mini Piles 3990 m |
25.07.2005 - 20.09.2005 |
-
| SUR YAPI INS. |
Selvice Houses Retaining Production |
Ø30 Mini Piles-Anchorages |
15.07.2005 - 02.08.2005 |
-
| KARABUK BELEDIYESI |
KARABUK Yesil District Municipality Social Facilities Soil Investigations |
Subsoil Investigation Boreholes |
10.07.2005 - 20.07.2005 |
-
| KARABUK BELEDIYESI |
KARABUK Kayacik Village,Soil Investigations |
Subsoil Investigation Boreholes |
28.06.2005 - 10.07.2005 |
-
| T.C KARAYOLLARI |
1st Division Branch Chief of Highways Department Mimar Sinan Housing Area Soil Investigations |
Subsoil Investigation Boreholes |
23.06.2005 - 05.06.2005 |
-
| TES-IS INS. |
Resinex Plastic Factory Construction under foundation piles |
Ø45 Mini Piles 2595.5 m, Ø35 Mini Piles 753 m |
24.06.2005 - 22.09.2005 |
-
| EDIRNE IL OZEL IDARESI |
Soil Investigation and Drillings Edirne Uzunkopru Bridge and New Bridge |
Subsoil Investigation Boreholes, Laboratory and in-situ Tests on Histroical Uzunkopru Bridge, 330m, New Bridge Route, 330m |
01.05.2005 - 15.06.2005 |
-
| GENC YAPI INS. |
Selimpasa - Kiyikent Genc Yuva Yap. Ins. Construction of Soil Improvement Project |
Ø30 Mini Piles 600 m ve Soil Improvement Design Project |
27.04.2005 - 15.05.2005 |
-
-
| EKSIOGLU APT. |
Tosmur Beldesi / ALANYA Indoor Mini Piles |
Ø30 Mini Piles |
01.03.2005 - 05.03.2005 |
-
| T.C.TOPLU KONUT IDARESI |
Karabuk Province, Cevizlidere Role Geotechnical Investigation For Slum Conversion Project |
Subsoil Investigation Boreholes |
02.02.2005 - 15.02.2005 |
-
| YAPIM INS. |
I.U. Capa Faculty of Medicine Parking Lot Construction |
Ø45 Mini Piles 3200 m, Anchorages 7000 m |
10.02.2005 - 15.04.2005 |
-
| ORIENT RESEARCH MUH. |
Selected High Important Buildings In Istanbul Feasibility Study and Consultancy Services For Supplementation |
Subsoil Investigation Boreholes, Geotechnical in-situ tests and reporting |
27.01.2005 - 10.03.2005 |
-
| FATIH APT. |
Tosmur Town / ALANYA Indoor Mini Piles |
Ø30 Mini Piles |
01.01.2005 - 05.02.2005 |
-
| AKOZ INS. |
Akoz Insaat Cennet Mansions Worksite Retaining Works |
Ø30 Mini Piles 1200 m, Anchorages 450 m |
30.12.2005 - 05.02.2005 |
-
| NEJAT GULER |
Sariyer Istanbul |
Ø30 Mini Piles |
20.11.2004 - 10.12.2004 |
-
| T.C.TOPLU KONUT IDARESI |
Halkali 3.Etap Toplu Konutlari Geotechnical Investigation for Landslide on Road District No. 42 |
Subsoil Investigation Boreholes |
17.12.2004 - 25.12.2004 |
-
| ISTANBUL UNI. DONER SERMAYE IST. |
Directorate of Provincial Public Works Istanbul wide Schools Drilling Investigations |
Subsoil Investigation Boreholes |
10.11.2004 - 28.12.2004 |
-
| CAN MEDIKAL A.S. |
Bagdat Cad. ISTANBUL |
Water Reservoir with Embedded Cantilever Shear Walls |
27.10.2004 - 27.11.2004 |
-
| EMEK MUH. |
Kosuyolu ISTANBUL |
Retaining Structure with Cantilever Shear Walls |
21.10.2004 - 02.11.2004 |
-
| SARBAY INS. |
Sarbay Ins. Silivri School Construction Site Piling Project and Application |
Ø40 Mini Piles 912 m |
21.10.2004 - 03.11.2004 |
-
| TEMELKON INS. |
Bagcilar Nihah Palace Productions Mini Piles |
Ø30 Mini Piles 1230 m |
15.09.2004 - 09.10.2004 |
-
| TEMTAS LTD. STI. |
Temtas Ins. Bagcilar Retaining Wall Piles Construction Site |
Ø25 - Ø30 Mini Piles 1000 m |
14.09.2004 - 29.09.2004 |
-
| TEKCELIK A.S. |
Beykent University Ayazaga Campus Construction Making Injection |
Injection 1200 m |
15.08.2004 - 07.09.2004 |
-
| HAS YAPI INS. |
P&G Depo Field Gebze/KOCAELI |
Ø30 Mini Piles |
20.12.2003 - 10.01.2004 |
-
| HASYAPI A.S. |
Sekerpinar P&G Depo plant worksite bored piles |
Ø35 Mini Kazık İmalatı 2400 m |
20.12.2003 - 25.01.2004 |
-
| ATAKAS INS. |
Gebze/KOCAELI Making Water Well Drilling for Atakas Insaat |
Water Well Drilling |
29.05.2003 - 10.06.2003 |
-
| ARCAN INS. |
5. Gazeteciler Site Levent/ISTANBUL |
Injection |
28.04.2003 - 10.05.2003 |
-
| ALTINSOY INS. |
Soil Investigation of Sekerpinar P&G Depo Plant Construction Site |
Subsoil Investigation and Pressuremeter |
25.03.2003 - 05.04.2003 |
-
| S.S GUNES YENI BELDEMIZ KONUT YAPI KOOP. |
Land Use Suitability Geological-Geotechnical Investigation Base Of B Cavuslu/SILIVRI Urban Development Plan |
Subsoil Investigation Boreholes, Laboratory Test and Reporting |
25.02.2003 - 30.03.2003 |
-
| GOKBORA A.S. |
Urunlu/BURSA Gokbora Depo Area Soil Improvement Project |
Ø60 Bored Piles - Ø30 Mini Piles |
01.08.2002 - 05.09.2002 |
-
| ALBES DERI SAN. A.S. |
Tuzla Leather Industry Soil Improvement Project |
Mini Piles, Injection |
01.06.2002 - 15.06.2002 |
-
| DOGA EVLER KONUT YAPI KOOPERATIFI |
Buyukcekmece County, The Village's Borders Karaagac 380,000 m2 area Study of Land Use Suitability |
500 m Borehole Drilling of Subsoil Investigation and Laboratory Tests |
23.11.2001 - 25.12.2001 |
-
| IMAMOGLU INS. |
Beylikduzu/ISTANBUL Imamoglu Insaat Soil Investigation Project |
Geotechnical Investigation |
02.07.2001 - 10.07.2001 |
-
| BIRLIK MUH. INS. LTD. STI. |
Tuzla/ISTANBUL Junction Bridge Projects Investigations |
Geotechnical Investigation |
21.06.2001 - 30.06.2001 |
-
| STY INSAAT |
Gelibolu-Eceabat Road Bridge Pile |
Gelibolu-Eceabat Road 4 Bridge Bored Pile (100 cm diameter 2500 m) |
15.12.2010 - 28.02.2011 |
-
-
| TUPRAS |
Resid Upgrading |
Bored Pile |
01/2012 - 06/2012 |
-
| OZD INSAAT A.S. |
Ali Fuat Pasa Gecisi Anchorage Retaining Wall Project |
Anchorage Retaining Wall |
01/2011 - 05/2012 |
|
|
|